How to estimate rehab costs

By Austin Frangoules | Updated | 5 min read

Estimate rehab costs in two passes. First, multiply the square footage by a per square foot rate for the scope of work, adjusted for your market and the age of the house. Then, once you walk the property, build a line-item budget from quantities and unit costs, add permits and a contingency, and check it against bids.

Two ways to estimate a rehab

A quick estimate gets you through the first screen in a minute. It answers one question: is this deal worth a walk-through? A line-item estimate takes longer but is the number you should offer on. Use the quick method to sort leads and the line-item method before you sign.

All the costs below are planning numbers for investor-grade finishes with contractor-direct pricing. They vary by market and contractor. Retail remodel prices can run much higher. Your own bids and closed jobs are always the better source.

The quick estimate: cost per square foot by scope

Pick the scope that matches the work, multiply by the heated square footage, then apply two multipliers: one for your market's labor and material costs, and one for the age of the house.

Rehab cost per square foot by scope (planning defaults)
ScopeDefault per sqftRangeTypical work
Cosmetic$20$15 to $30Paint, LVP, fixtures, hardware, landscaping, deep clean
Light$35$25 to $40Cosmetic plus kitchen refresh (counters, appliances) and bath refresh
Medium$55$40 to $75Light plus new kitchen, 1 to 2 full baths, HVAC or roof, some windows
Heavy$90$75 to $110Medium plus roof and HVAC, panel, plumbing, windows, layout changes
Gut$125$100 to $150To the studs: all systems, drywall, insulation, framing repairs
  • Market multiplier: 1.00 is the baseline. Higher-cost metros run above it, for example about 1.20 in Northern Virginia, and resort areas with scarce labor can run about 1.10. Some rural markets run a little below.
  • Age multiplier: 1.15 for homes built before 1950, 1.05 for 1950 to 1978, and 1.00 for newer homes. Older houses hide more surprises.
Example | Quick estimate for a light rehab
1,400 sqft x $35 (light scope)
$49,000
x 1.05 market multiplier
$51,450
x 1.05 age multiplier (built 1965)
$54,022.50
Range using $25 to $40 per sqft
$38,587.50 to $61,740
Contingency at 10% (light scope)
$5,402.25
Quick rehab budget$59,424.75

Planning numbers. Use this to decide whether to walk the house, not to set a final offer.

The line-item estimate: quantity times unit cost

On the walk-through, list every item of work with a quantity. Multiply each by a unit cost, add them up, apply your market multiplier, then add permits as a share of that hard cost. This is the number that should drive your offer.

Common rehab line items (planning unit costs, vary by market and contractor)
Line itemUnitDefaultRange
Demo and dumpsterper 30-yard$650$500 to $800
Roof, architectural shingle tear-offper sqft of roof$6.00$4.50 to $8.00
HVAC system, heat pump, ducts reusedeach$9,000$7,000 to $13,000
Water heatereach$1,800$1,400 to $2,600
Electrical panel upgradeeach$2,800$2,000 to $4,000
Full rewireper sqft$7.00$5 to $10
Plumbing repipe (PEX)per sqft$5.00$4 to $8
Windows, vinyl, installedeach$650$450 to $900
Interior paint, walls, trim, ceilingsper sqft of floor$3.00$2.50 to $4.50
LVP flooring, installedper sqft$5.00$4 to $7
Kitchen (cabinets, quartz, backsplash, fixtures)each$18,000$12,000 to $30,000
Full batheach$10,000$7,000 to $18,000
Crawlspace encapsulationeach$7,500$4,000 to $15,000
Permits and plans% of hard cost2%1% to 4%
Final clean and puncheach$750$500 to $1,200
Example | Line-item estimate for a systems and finishes job
Roof: 1,800 sqft x $6
$10,800
HVAC $9,000, water heater $1,800, panel $2,800
$13,600
Windows: 12 x $650
$7,800
LVP: 1,000 sqft x $5
$5,000
Interior paint: 1,400 sqft x $3
$4,200
Hard cost (market multiplier 1.00)
$41,400
Permits at 2% of hard cost
$828
Rehab before contingency
$42,228
Contingency at 15% (medium scope)
$6,334.20
Line-item rehab budget$48,562.20

Planning unit costs. Replace each with a quote once you have one.

Pick the right contingency

Contingency is money you plan to spend on what you cannot see yet: rot under the tub, a bad sewer line, a panel the inspector rejects. Size it by risk, not by hope.

  • Cosmetic and light: 10%.
  • Medium: 15%.
  • Heavy: 20%.
  • Gut: 25%.
  • Built before 1950, or any structural work: add 5%.
  • A signed contractor bid: about 10%, since the bid already prices the scope.

Budget profit as if the contingency gets spent. If it does not, that is upside, not the plan.

What to look for on the walk-through

The expensive surprises hide in a few places. Check them before you trust any number:

  • Roof age and soft spots, and attic stains.
  • HVAC age and the data plate on the water heater.
  • The electrical panel brand and capacity. Some older panel brands usually need replacing.
  • Plumbing material. Cast iron drains and polybutylene supply lines in older homes often mean a repipe.
  • Crawlspace moisture, termite damage and sagging floors.
  • Whether the house sits in a flood zone, which changes insurance and sometimes what you may build.
  • Work done without permits, which can force rework at inspection.

Turn the estimate into a schedule and bids

An estimate becomes real when contractors bid each line. Compare bids line by line against your budget, not just the total. Once work starts, approve every change order in writing, collect a lien waiver with each payment, and keep the punch list short by inspecting as you go.

After each job, compare what you estimated to what you spent. Run The Deal's rehab engine can blend your actual job costs into its unit costs, weighting newer jobs more, so the next estimate starts from your real numbers instead of a generic default.

Common mistakes

  • Using retail remodel prices from consumer sites for an investor rehab, or the reverse.
  • Skipping the age multiplier on a pre-1950 house.
  • No permits line. Permits and plans are a real cost, and unpermitted work can cost more later.
  • Zero contingency because the house looks clean.
  • Pricing finishes above the neighborhood. Match the finishes in your comps, not your own taste.
  • Forgetting the rehab drives the timeline. More scope means more months of holding costs.

Put the rehab into the full deal with our fix and flip budget template. Build your estimate line by line in the free rehab cost estimator, then run your numbers in the free flip calculator.

Questions

How much does a rehab cost per square foot?

As planning numbers for investor-grade work: about $20 for cosmetic, $35 for light, $55 for medium, $90 for heavy and $125 for a gut rehab, before market and age adjustments. Real costs vary by market and contractor.

How accurate is a per square foot rehab estimate?

Good enough to screen a deal, not to set a final offer. The range for each scope is wide. Walk the house and build a line-item estimate before you sign.

How much contingency should a rehab have?

A common planning range is 10% for cosmetic and light work, 15% for medium, 20% for heavy and 25% for a gut, plus about 5% for pre-1950 homes or structural work.

Should I include permits in my rehab estimate?

Yes. A planning default is about 2% of hard cost, with a range of 1% to 4%. Check your local building department for the work you plan.

For education only. Not legal, tax, lending or investment advice. Loan programs and guidelines change and vary by lender; confirm current terms with your lender.